ANN VILLA & ESTATE VILLA PROJECT IN UNGASAN
which has started from end of June 2013,
Now we are going to concrete work, Sloof, and Coloms 1st floor.
Foundation works, we putLimestone about 100 dump truck,
to get more high ground level.
Concrete work starts,
the shape of the building will see.
We plan to finish the concrete construction work for 1st floor
columns, beams and2nd floor after that we are going on
vacation of Ramadan!
which has started from end of June 2013,
A unit front to Garage view |
Now we are going to concrete work, Sloof, and Coloms 1st floor.
Foundation works, we putLimestone about 100 dump truck,
to get more high ground level.
Concrete work starts,
the shape of the building will see.
We plan to finish the concrete construction work for 1st floor
columns, beams and2nd floor after that we are going on
vacation of Ramadan!